98 Street Closed near 90 Avenue

Southbound 98 Street Closed near 90 Avenue

Updated August 16, 2018

The contractor has amended the road closure after running into some delays. In order to complete the tie in the partial closure will have to continue through Saturday, August 18. The road should be completely reopened by Sunday.

Background

August 13, 2018
A portion of southbound 98 Street, just south of 90 Avenue will be closed for two days beginning on August 15, 2018.

During that time vehicles can detour along 94 Street (River Road). 98 Street is expected to reopen on August 17.

The closure is part of the Town of Peace River’s Slide Remediation project along 99 Street. Construction crews need to tie in a sanitary sewer line and to do this they require closing the road. We apologize for the inconvenience during this time.

The road is expected to reopen on August 17.

Related

For information on the 99 Street Slide Remediation project, tap or click the link below.

99th Street Slide Remediation